If 12 workers complete a task in 15 days, how many days will 20 workers take at the same rate?
Select an option. Your answer will be checked instantly.
Correct Answer: D. 9 days
Explanation:
Workers and time are inversely proportional for fixed work.
Thus, 12 × 15 = 20 × days, giving 9 days.