Question
If 15 workers finish a job in 20 days, how many workers are needed to finish it in 12 days?
Select an option. Your answer will be checked instantly.
Correct Answer: D. 25 workers
Explanation:
Worker-days remain constant for the same job.
Thus, 15 × 20 ÷ 12 = 25 workers.