Question
A team completes 40% of a project in 12 days. At the same rate, how many more days are needed?
Select an option. Your answer will be checked instantly.
Correct Answer: D. 18 days
Explanation:
If 40% takes 12 days, 10% takes 3 days.
The remaining 60% takes 18 days.