Question
In a resource-allocation graph, an edge from a process to a resource indicates what?
Select an option. Your answer will be checked instantly.
Correct Answer: C. The process is requesting an instance of that resource
Explanation:
A process-to-resource edge is a request edge showing an outstanding demand.
An assignment edge points in the opposite direction, from a resource instance to a process.