NCRE Level 4 system-design analysis 62: Which conclusion about software project risk is most accurate? Focus on software engineering in this variation.
Select an option. Your answer will be checked instantly.
Correct Answer: A. Risk management identifies uncertain events, estimates impact and plans mitigation or response
Explanation:
Proactive risk work helps teams reduce likelihood, impact or recovery time.